Technical Details

  1. Overall Concept and Design 
  2. Building Construction 
  3. Heating, Ventilation & Air-Conditioning (HVAC) System  
  4. Water 
  5. German Passivhaus Standard 
    1. Passive House requirements 
    2. The following five basic principles apply for the construction of Passive Houses: 

Overall Concept and Design 

The EcoHouse concept was to have a family home in a holistic environment, marrying sustainability,  energy and water conservation with comfort and a strong connection to the land around it. The primary  energy conservation concept is that of the German Passivhaus (see below for details). Connection to the  surrounding land is reinforced via growing plants either direct rooted in the earth or in pots on paved  terraces.  

The house was designed by the Austrian architect, Elisabeth Kahlen, based in Graz, who is a specialist  in low energy buildings. The Passivhaus energy consumption calculations on her design were made  using the approved Passivhaus calculation tool – PPHP – and confirmed that the building conformed to  the Passivhaus energy requirements.  

The original design was for a three-storey building, with the lowest floor usable as a meeting area for  presentations on Passivhaus and energy conservation in general. That floor was also designed to house  the HVAC equipment and normal household utilities (storage and laundry facilities). The outline  drawings were passed to the Montenegrin builder, who was also a registered structural engineer, to  provide the final drawings for building permission. He changed the location of the bottom floor to a  separate strong reinforced concrete structure to the west of the rest of the house. He deemed this change  to be essential to support the main house and so satisfy the earthquake requirements for the building  permission.  

Building permission was granted in December 2012, with construction starting at the end of January  2013. The owners moved into the house in the spring of 2014.  

Building Construction 

Outside walls have 20cm thermal brick between the reinforced concrete frame (legally required for this  active earthquake zone), all clad with a 12cm EPS layer of insulation. Use of a more environmentally  friendly insulation material was considered, but costs, easy availability of alternatives, and the local  tradesmen’s inability to install anything other than EPS made this material the only option. Thermal  bridging to the first floor terrace and its supporting columns is minimised by extending the insulation to  cover all these surfaces. 

Windows are all triple-glazed (4-16-4-16-4) and argon gas filled to a Rehau profile manufactured and  installed under licence by VH Montenegro (https://www.vhmsolutions.me/), with external roller  shutters to help heat loss/ gain. The windows have U values between 0.88 and 1.1W/mK. The windows  were installed with additional air-tightness tape around the frames to further reduce air leakage. While  the heat transfer rate is higher than the Passivhaus requirement of 0.8W/m2K, this was the best available  in the country at the time of construction. 

The south side of the house has wide overhangs over each of the two floors, designed to reduce direct  sunlight hitting the windows in summer, and maximise sunlight entry in winter. This reduces solar gain  in summer, while allowing it in winter, both being passive methods of energy conservation. 

Although installation of photovoltaic solar panels was uneconomic at the time of construction, ducting  was installed from the roof to the solar panel control room at the garage. This allows easy installation  of photovoltaic solar panels in future. There is space in the room for energy storage equipment (eg  batteries) and the associated control equipment.  

It was not possible to carry out an air-tightness test on the building at the appropriate time, as there were  no qualified personnel and equipment available within economic reach. This means that it has not been  possible to prove official conformity to the Passivhaus standard. 

Heating, Ventilation & Air-Conditioning (HVAC) System  

There is an integrated heating and cooling system with a Daikin 10kW air-to-water heat pump as the  energy provider. The original heat pump was rated at 7.1kW for heating, 7.8kW for cooling, with a  Coefficient of Performance (COP) of 2.4. The pipework as installed had too many bends from the heat  pump, which reduced its effectiveness, and it was up-rated. Heating is through Rehau under-floor  distribution controllers and water pipes, while cooling is via fan coils in the ducted ventilation system., A Systemair ventilation recuperative unit constantly recycles the internal air, drawing in about 25%  external fresh air through a heat exchanger. Extraction points are in both toilets, as well as on the upper  floor. 

Domestic hot water is heated by a single Viessmann 2.5m2roof-mounted solar panel, set at 35º to the  horizontal, feeding a Viessmann 160l tank, with auxiliary electrical heating. The whole HVAC and hot  water installation was designed and installed by Ening d.o.o. of Nikšić (http://www.ening.co.me/). 

The end result is a very comfortable interior environment (see a summary of electricity consumption below). The internal temperature in winter and summer is between 23°C to 25°C compared to mid to  high 30°sC, sometimes over 40C°, outside during June to early September. The outside winter  temperature is usually in the low teens, down to 5°C at times during December to February. Frosts are  (fortunately) rare, but cause havoc with the garden if they last longer than a few hours. The original  PHPP calculations were made using 20ºC as the internal temperature, with temperatures over 25ºC rated  as occurring for 10% of the year, using Roma Practica di Mare data as the basis for climate.  

Ducting input air to the heat pump via an underground pipe, as recommended in standard Passivhaus  literature, was not possible due to the layout and soil of the site. A minimum of 30m is required at a  depth of at least a metre. There was not enough space. Additionally, a layer of insulation underneath the  reinforced concrete foundation was not within the capabilities of the building team, quite apart from the  additional cost. 

Water 

Water conservation was an important part of the overall concept for the EcoHouse. The public water  supply suffers shortages, especially in summer at the height of the tourist season.  

A severe storm can give 30 to 40cm of water over a 24-hour period, and 10cm to 20cm is normal for an  average storm. Risan’s annual precipitation from 1961 to 1984 was 3.1metres, most of which seems to  fall at once! 

While normal domestic consumption is not large, with only two people living in the house, the garden  needs a substantial amount of watering in summer. The garden areas are not contiguous, being around  the perimeter of the house, and there is an 8m difference in height from the north side (back) to the south  side (front). 

An underground 15m3tank was built on the east side of the house to collect rainwater from the roof.  This water is pumped to the garden areas on the north side of the house, including the section along the  roadside, feeding a comprehensive piped drip irrigation system, allowing more precise and controlled  water flow to plants. The main piped system covers all the sections of the garden and uses the main  water supply, with battery-operated timers allowing different times and durations for the 10 zones. 

Heat recovery from domestic hot water was considered, but the equipment and installation required was  deemed uneconomic for the small amount of heat recovered. 

While the main water is drinkable, drinking water is collected from a spring 200m above sea-level about  2km from the house. This spring (Smokovac) is used by many of Risan’s residents. 

German Passivhaus Standard 

From https://passivehouse.com/02_informations/02_passive-house-requirements/02_passive-house requirements.htm 

Passive House requirements 

For a building to be considered a Passive House, it must meet the following criteria ( for detailed  criteria, please see the building certification section)

1. The Space Heating Energy Demand is not to exceed 15 kWh per square meter of net living space  (treated floor area) per year or 10 W per square meter peak demand. In climates where active cooling is  needed, the Space Cooling Energy Demand requirement roughly matches the heat demand  requirements above, with an additional allowance for dehumidification. 

2. The Renewable Renewable Primary Energy Demand (PER, according to PHI method), the total  energy to be used for all domestic applications (heating, hot water and domestic electricity) must not  exceed 60 kWh per square meter of treated floor area per year for Passive House Classic.  

3. In terms of Airtightness, a maximum of 0.6 air changes per hour at 50 Pascals pressure (ACH50), as  verified with an onsite pressure test (in both pressurized and depressurized states). 

4. Thermal comfort must be met for all living areas during winter as well as in summer, with not more  than 10% of the hours in a given year over 25°C. For a complete overview of general quality  requirements (soft criteria) see Passipedia.  

All of the above criteria are achieved through intelligent design and implementation of the 5 Passive  House principles: thermal bridge free design, superior windows, ventilation with heat recovery, quality  insulation and airtight construction.  

The following five basic principles apply for the construction of Passive Houses: 

Thermal insulation 

All opaque building components of the exterior envelope of the house must be very well-insulated. For  most cool-temperate climates, this means a heat transfer coefficient (U-value) of 0.15 W/(m²K) at the  most, i.e. a maximum of 0.15 watts per degree of temperature difference and per square metre of exterior  surface are lost. 

Passive House windows 

The window frames must be well insulated and fitted with low-e glazings filled with argon or krypton  to prevent heat transfer. For most cool-temperate climates, this means a U-value of 0.80W/(m²K) or  less, with g-values around 50% (g-value= total solar transmittance, proportion of the solar energy  available for the room). 

Ventilation heat recovery

EcoHouse Montenegro Technical Details.docx page 3of 4 

Efficient heat recovery ventilation is key, allowing for a good indoor air quality and saving energy. In  Passive House, at least 75% of the heat from the exhaust air is transferred to the fresh air again by means  of a heat exchanger. 

Airtightness of the building 

Uncontrolled leakage through gaps must be smaller than 0.6 of the total house volume per hour during  a pressure test at 50 Pascal (both pressurised and depressurised). 

Absence of thermal bridges 

All edges, corners, connections and penetrations must be planned and executed with great care, so that  thermal bridges can be avoided. Thermal bridges which cannot be avoided must be minimised as far as  possible. 

Passive House buildings are planned, optimised and verified with the Passive House Planning  Package (PHPP).

Electricity Consumption 

The internal liveable area of the house is 59.33m2 + 54.26m2, total 113.59m2. This results in an expected  consumption of 37.34kW per day. The actual electricity consumed over the period January 2015 to  December 2024 averages 9.9% more than the standard Passivhaus requirement of 120kW per m2 per  year. The actual internal temperature, though, is between 23ºC to 25ºC compared to the standard as used  in the PHPP calculation of 20ºC, ie 20% higher. 

It is therefore reasonable to state that the house performs close to the Passivhaus requirement.